Jubilee Stadium will get a giant 98 square-metre video screen, gifted to Georges River Council by the NSW Office of Sport.
Screw Piling Solutions (SPS) worked closely with Bekker Engineering to come up with a cost effective and speedy screw pile design solution for this time driven project.
SPS were onsite a few days after being given the go ahead. 20 Large screw piles were driven through the filled ground to anchor the massive screen in place. This was completed in one day (30th Sept 2019) allowing formwork and reinforcing to be started immediately, then followed by the pouring of the slab.
This speedy installation allowed enough time for the slab to cure and the massive screen installed prior to the start of the soccer season in Nov 2019.